PUBLIC NOTICE: Road Work Notice

1

Road work will be ongoing on Friars Hill Rd and Sir George Walter Hwy and will affect the flow of traffic in some areas.

Traffic Management Plan: 

Work on Friars Hill Road:

1.) WEEKEND WORKS – 

Paving  works is scheduled to take place from Electric Avenue to south of Epicurean Drive working on the Northbound lane (Ln). This will take a day with the use of single Ln traffic and temporary traffic lights. 

Date: Saturday 28th March 2020

Time: 7:00am – 3:30pm

Duration: 1 day

2.) WEEK DAY WORKS –

When paving work is complete between Electric Avenue and Epicurean Drive, roadworks will begin between Epicurean Drive to village walk Shopping Centre (northbound lane) and will take about four (4) days. Similarly single Ln traffic will apply and temporary traffic lights will be in place. 

Duration: 4 days

Time: 7:00am – 3:30pm

 

Work on Sir George Walter Hwy:

1.)

Roadworks near the solar farm will switch to the northbound Ln and will continue in the same area for the rest of the week. There will be single Lane Traffic with use of temporary Traffic Lights.

Time: 7:00am- 3:30pm 

Duration: 1 week

 

2.)

 When paving near Solar farm is complete, roadworks will begin near Unicomer. This will take the remainder of the week with the works beginning today (Tue).

Date: Tuesday 31st March 2020

Time: 7:00am- 3:30pm

Duration: 1 week

To avoid traffic congestion during peak hours; the motoring public may use Barnes/Powell’s route to get to and from V.C Bird Int. Airport.  Road usurers are urged to proceed with caution. 

Advertise with the mоѕt vіѕіtеd nеwѕ ѕіtе іn Antigua!
We offer fully customizable and flexible digital marketing packages.
Contact us at [email protected]

1 COMMENT

  1. This is an excellent 7 days to get all road works done- since less traffic will be on the road. After Easter there should be no delays on road, and traffic lights not working…..

Comments are closed.