Paving Continues – Road Infrastructure Rehabilitation Project

0
Please note the weekly look ahead for 29th July, 2019- 2nd August, 2019:

 

This week, paving continues in phase 1C of FHR.

 

Drainage works to continue in phase 1C of FHR.

Drainage works to continue in phase 1A of SGWH.

 

Traffic Management: ‘Reduced width Lanes’/ ‘stop and go traffic’.

 

Specific areas:

 

FHR

Drainage works to continue in phase 1D and phase 2 of FHR. This will result in driveway closures between Cedar Valley Junction and West Indies Oil Pond and Sunshine Ice Cream, Rd.

Date: Monday 29th July 2019

Duration: 2 days

Diversion: N/A

 

SGWH

Drainage works to continue in phase 1A. This will result in driveway closure at Oasis/ Mi Casa Warehouse

Date: Sunday 28th July 2019

Duration: 7:00am – 3:30pm

Diversion: N/A

 

Upcoming Road closures

 

Road closure scheduled at Hodges Bay Rd. This is to facilitate drainage works in this area.

Date: Wednesday 31st July 2019

Duration: 2 days

 