NOTICE: Road Works Update

0
ROAD WORK UPDATE- ROAD CLOSURE!!
A section of Friars Hill Road will be closed on the weekend:
On Saturday 20th July, 2019    TIME: 7.00am on  to 6.00pm.
There will be a closure at phase 1C between Arnold Williams Drive and Cedar Valley Junction. This is to facilitate carriageway construction in that phase. Road users are asked to obey the signage and exercise extreme caution. The road will be opened back up on Sunday, 21st July 2019 from 7am to 6:00pm and the closure will resume at 7am on Monday, 22nd July, 2019 for a duration of 2 weeks. The diversion is attached.
Please also note the weekly look ahead below:

Weekly Lookahead for 22nd July – 26th July, 2019.

 

This week, carriageway construction begins in phase 1C on FHR.

 

Drainage works to continue in phase 1A of SGWH.

 

Traffic Management: ‘Reduced width Lanes’/ ‘stop and go traffic’.

 

Specific areas:

 

SGWH

Drainage works to continue in phase 1A. This will result in driveway closures between LIAT Building and Solar Farm.

Date: Monday 22nd July, 2019

Duration: 1 week

Diversion: N/A

 

Single Lane closure at Phase 1A of SGWH between Henderson 2004 and Oasis Water Warehouse. This is to facilitate carriageway works.

 