The road work plan for the week ahead (7th October to 11th October 2019) will see an ongoing road closure. Work to complete a roundabout in phase 1A (Cedar Grove and Friars Hill Road junction). Temporary traffic lights will be in use.
Duration: 1 week
Diversion: Single Lane Traffic with use of traffic lights (Marble Hill Road).
- Monday 7th October
Carriageway construction (Milling/Baseworks) scheduled to begin in Phase 1D (between Cedar Valley Junction and W.I.O Pond.)
Duration: 1 Week
Drainage works will be undertaken in the following areas:
- Tuesday 8th October
Driveway Crossings in Phase 2 near Village Walk Duration/Time: 7:00am – 3:00pm
- Wednesday 9th October
Driveway Crossing at Jr’s Sports Bar Duration: 7:00am -3:00pm
- Thursday 10th October
Side Road Culvet installation at Summer Lane Duration: 7:00am – 3:00pm
- Friday 10th October
Side Road Culvert at Gambles Medical Center Duration: 7:00 am- 3:00pm
Works on Sir George Water Hwy: Monday 7th October 2019
Carriageway construction will continue in phase 1A of from VC. Bird International Airport – Liat Office (Northbound Lane) Single lane traffic with use of traffic lights
Duration: 1 week