Progress is being made on the installation of a new two-million-gallon reverse osmosis (RO) plant at Shell Beach, according to the Antigua Public Utilities Authority (AUPA).
As part of the project, workers are preparing to lay around 3,300 feet of high-density polyethylene (HDPE) transmission lines. The pipeline will run from Jabberwock through Cedar Valley, linking the new facility to the wider water distribution network.
Once installed, the system is expected to strengthen water supply to communities along the island’s northern corridor.

AUPA said the initiative forms part of its wider efforts to modernise water infrastructure and improve reliability across Antigua and Barbuda.
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
CLICK HERE TO JOIN OUR WHAT’S APP GROUP
Advertise with the mоѕt vіѕіtеd nеwѕ ѕіtе іn Antigua!
We offer fully customizable and flexible digital marketing packages.
Contact us at [email protected]
Glad we’re getting more water security, but I hope they’re also considering the environmental impact of another desalination plant.
APUA deserves credit here. Laying down over 3,000 feet of pipes is no small job, this is real progress.
This update seems no different from the inlet last week. Tell me how much closer they are from then to now
It’s good to see the project moving forward. Hope it’s completed on time and properly maintained to serve the community long-term.
APUA needs a pat on his back. Listen. I can see they are trying
Comments are closed.