The traffic management plan for road works for the week ahead – from 1st to 5th Jun, 2020 will see road closures on both FriarsHill Rd and Sir George Walter Hwy as roadworks continue on both roads under the Government of Antigua and Barbuda Road Infrastructure Rehabilitation Project.
24 HR ROAD CLOSURE:
Roadworks will be undertaken in phase 3B on a section of Friars Hill Road between Mahogany Dr to Rohan Henry St. This will result in a full road closure lasting about three (3) weeks.
Date: Tuesday 2nd June 2020
Duration: 3 Weeks
Time: 24hr closure from 7:00 am
Traffic Management: Traffic will be diverted accordingly
Diversion: Rohan Henry St. and Summer Ln.
Work on Sir George Water Hwy will also result on fill road closure last about two (2) weeks.
Road Closure
Road works will continue in phase 2A on a section of Sir George Walter Hwy between south of Dees Junction to Utopia Park Apartments.
Duration: 2 Weeks
Diversion: Mahico Drive, Old Parham Road